3R PETROLEUM ÓLEO E GÁS S.A. (“3R” or “Company”) (B3: RRRP3), in compliance with the provisions of CVM Resolution No. 44, and in addition to the material fact disclosed on February 28, 2023, informs its investors and the market in general that the root cause of the unit shutdown was solved, and the 3R-2 unit’s power generation and supply system (TLWP Platform) was re-established.
The wells operational resumption process has started and should be completed, gradually, in the coming days. At this time, 3R’s technical area is carrying out tests on the platform’s automation systems to ensure the safe resumption of production. Before the stoppage, the Papa Terra Cluster was producing with four wells and average daily production close to 17 thousand barrels of oil.
Finally, 3R reinforces its commitment to keep its investors and the market in general duly informed, in line with the best corporate governance practices and in strict compliance with the legislation in force.